Burndown chart
A burndown chart plots the work remaining in a sprint or project against time, so that the actual rate of completion can be compared with the rate required to finish on schedule.
Definition
Burndown chart: A burndown chart plots the work remaining in a sprint or project against time, so that the actual rate of completion can be compared with the rate required to finish on schedule.
In practice
How Burndown chart is used
The chart has remaining work on the vertical axis and time on the horizontal, with an ideal line falling steadily to zero at the end of the period. Its purpose is not to look tidy — real burndowns rarely do — but to make the gap between the required rate and the actual rate visible early enough to act on.
Shapes carry meaning. A flat line for most of the sprint followed by a cliff at the end usually means work was started in parallel and finished together, which is a work-in-progress problem: everything was in flight and nothing was done. A line that rises indicates scope was added mid-sprint. A line that drops in a single step suggests items are too large to show progress until they complete.
Burndown says nothing about what is being burned down. A sprint that hits zero by descoping the difficult item is indistinguishable, on the chart alone, from one that finished everything. This is why burndown is read next to scope change and carry-over rather than presented as a verdict.
Its close relative, the burnup chart, plots completed work and total scope as two separate lines. It is generally more honest for longer horizons, because scope growth appears as a rising ceiling instead of being silently absorbed into a single remaining-work line.
Marvex generates burndown from SALT or Jira sprint data and pairs it with scope change and carry-over in the sprint report, so a chart that reached zero can be checked against what was added or removed to get there.